All the laundries have been prepared but due to some technical problems (like law pressure of the water in the pipes and the weak electricity system), IBC had to make some improvements to the laundries, like buying and installing water tanks and water pumps for each laundry container and also the electricity system had to be changed with a three phased one.
IBC provides the baskets in the laundry and all the necessary cleaning materials and powders for a period of 9 months, from the starting date.
- Placing refuse containers for solid waste (garbage boxes)
(Isfahan1, Isfahan2, Qom1, Qom2)
100 covered garbage boxes (80cm and a diameter of 50cm) from metal were provided for the 4 camps, as following: 28 for Qom1, 22 for Qom2, 20 for Isfahan1 and 30 for Isfahan2.
- Installing playgrounds
(Isfahan2, Qom1, Qom2)
Due to the fact that in the camps Isfahan1 the Isfahan province provided playgrounds and in the Shehrdari camp other NGO has provided this facility, remained only the camps Qom1 and Qom2, with no facility and Isfaha2, where the number of children is high and the playground facilities are not sufficient.
B. OTHER ACTIVITIES
1. Supplies for the Bam Health Center
Supplies for Bam Health Center (the products targeted only the pregnant women and the new born babies and infants). The supplies were delivered to the Center to Mrs.Bahadori on the 24 th of April 2004 . List of supplies:
120 pieces of baby cloth (new born)
1.500 pieces of baby cloth (1 year old)
1.620 pieces of baby dippers
1.620 pieces of baby soap
1.620 pieces of baby shampoo
1.008 toothpastes
996 toothbrushes
1.000 shampoo for women
1.000 soap for women
1.044 underwear for women
300 slippers for women. |

IBC-Trocaire hygienic material
submitted to Bam Health Center-Ana Oprisan-IBC Field Coordinator-Mrs Bahadori-Bam Health Representative
|
2. Community Rehabilitation and Save building training program – For this project, IBC has signed a contract with CRS – Catholic Relief Services and for the awareness raising activities of the project it will be involved IBC's Iranian partner the Green Front of Iran. This project includes the coming of 2 Indian experts in safe building which will bring special machines for fabricating the safe bricks to be used in the permanent housing rehabilitation. IBC consulted the Task force forward to decide the place of implementation and there was decided for a piece of land in Baravat, provided by the governor Burunabadi.
3. Reconstruction of a health Center – IBC has a MoU with Kerman University – Faculty of Medicine, for the reconstruction of Razmandegan Health Center . The donor is Maltezer / Germany .
C. PLANNED ACTIVITIES
- Construction of one prefab school for Bam Education Office – IBC has submitted a dossier with different types of prefab school designs and the representative of Bam Education Office, Mr.Zanghiabadi, choose one of the designs. IBC is presently in mitigation with the donor for the planning of this project.
- Permanent shelters – this project is presently under mitigation with the donor and targets the construction of approximately 500 houses in an area to be decided by the local authorities in partnership with IBC.
CONTACT of IBC OFFICE IN BAM
Coordinator: Ana Opriþan
Address: Bam, Turkish container camp Isfahan 1, container no 120
Tel./Fax : 0344 – 231 07 70
Mobile: 0912 380 45 32
E.mail: ana@bluecrescent.net